Changes from 04/02/2025 to 04/09/2025

  • Thursday, April 3, 6:00 a.m. to 8:00 a.m. - completed
    Updating datacentre servers.
    User Impact: Long lived connections might get disconnected while the active to standby failover happen.
  • Thursday, April 3, 6:30 a.m. to 8:00 a.m. - completed
    Applying assorted fixes and features to Adobe AEM.
    User Impact: AEM author production needs to be restarted between 6:30 am and 8:00 am. https://www.torontomu.ca won't be affected.
  • Thursday, April 3, 7:00 a.m. to 10:00 a.m. - completed
    Updating Matlab.
    User Impact: Users will not be able to launch software during the upgrade. A short outage is expected. 
  • Friday, April 4, 6:00 a.m. to 7:30 a.m. - completed 
    Updating Mass Mail Tool.
    User Impact: Mass mail tool will be unavailable for few minutes. Please avoid scheduling any mass mail in the application before 8am on April 4.
  • Friday, April 4, 7:00 a.m. to 8:00 a.m. - completed
    Updating application server.
    User Impact: No access to CATIA for the time period.
  • Sunday, April 6, 9:00 a.m. to 5:00 p.m. - completed 
    Updating network hardware on ENG - 4th floor (North).
    User Impact: All networked devices at ENG 4th floor north will be disconnected for network switches upgrade.
  • Tuesday, April 8, 9:00 a.m. to 9:30 a.m. - completed 
    Updating UPO dashboards.
    User Impact: This change will only impact UPO Dashboard/Report users.

Changes from 04/09/2025 to 04/16/2025

  • Thursday, April 10, 8:00 a.m. to 8:30 a.m. - completed
    Updating Content 7 servers.
    User Impact: Content 7 Experience (web access) will be down, and document uploads will be unavailable during the outage.
  • Thursday, April 10, 6:00 p.m. to 8:00 p.m. - completed
    Updating application server.
    User Impact: Coldfusion, TAI and other apps hosted on CCS server will be unavailable.
  • Friday, April 11, 7:00 a.m. to 8:00 a.m. - completed
    Updating TMU's Resource and Identity Management System
    User Impact: Access to Activation, Self Service and Admin will be intermittent during this period.