- 06/28/2023 to 07/05/2023
- 07/05/2023 to 07/12/2023
- 07/12/2023 to 07/19/2023
- 07/19/2023 to 07/26/2023
- 07/26/2023 to 08/02/2023
Changes from 06/28/2023 to 07/05/2023
- Thursday, June 29, 6:30 a.m. to 8:00 a.m. - completed
Applying assorted fixes and features to Adobe AEM.
User Impact: None expected as www.torontomu.ca won't be affected. - Friday, June 30, 6:00 a.m. to 8:00 a.m. - completed
Updating AEM.
User Impact: The www.torontomu.ca will not be affected. The cmshost and cqauthor.dev will not be available between 6 a.m. to 6:30 a.m. - Friday, June 30, 8:00 a.m. to 8:30 a.m. - completed
Removing Eduroam login ability with @ryerson.ca usernames.
User Impact: Users can currently login with @torontomu.ca.
Changes from 07/05/2023 to 07/12/2023
- Thursday, July 6, 9:00 a.m. to 3:00 p.m. - completed
Updating TRS EMS production server
User Impact: TRS users are aware of this Event management application update.
Changes from 07/12/2023 to 07/19/2023
- Thursday, July 13, 6:30 a.m. to 8:00 a.m. - completed
Applying assorted fixes and features to Adobe AEM.
User Impact: None expected as www.torontomu.ca won't be affected. - Friday, July 14, 6:30 a.m. to 7:30 a.m. - completed
Upgrading CAS server software.
User Impact: Access to CAS maybe intermittent during this period. - Monday, July 17, 8:00 a.m. to Friday, July 21, 5:00 p.m. - completed
Updating SIEM.
User Impact: None expected.
Changes from 07/19/2023 to 07/26/2023
- Friday, July 21, 12:01 a.m. to Monday, July 24, 8:00 a.m. - completed
Upgrading eHR.
User Impact: eHR and all related functions will be down during the outage. - Friday, July 21, 7:00 a.m. to 7:15 a.m. - completed
Updating system software for Green pages and Finance forms apps.
User Impact: Access to Green, White pages and Finance forms apps will be intermittent.
Changes from 07/26/2023 to 08/02/2023
- Wednesday, July 26, 5:00 p.m. to 6:00 p.m. - completed
Updating Content 7 server.
User Impact: The Content 7 application will be unavailable during this time period. - Thursday, July 27, 6:30 a.m. to 8:00 a.m. - completed
Applying assorted fixes and features to Adobe AEM.
User Impact: None expected as www.torontomu.ca won't be affected. - Thursday, July 27, 9:00 p.m. to 9:30 p.m. - completed
Updating ColdFusion.
User Impact: All applications at *.cf.ryerson.ca will be unavailable. - Friday, July 28, 6:00 a.m. to 8:00 a.m. - completed
Upgrading WordPress.
User Impact: The blog.torontomu.ca network will be unavailable briefly (<10 minutes) while the application updates. Subsequently, each blog will experience a brief (<1minute) outage as it is upgraded. - Friday, July 28, 7:00 a.m. to 8:00 a.m. - completed
Updating TMU Resource and Identity Management System.
User Impact: Access to Activation, Self Service and Admin will be intermittent during this period. - Sunday, July 30, 11:00 a.m. to 1:00 p.m. - completed
Updating MyServiceHub.
User Impact: There will be no outage to MyServiceHub.